Stakeholder Interaction > NSP Consultations > Integral Energy Final Report for New Large Network Asset – Establishment of West Parramatta Zone Substation

Integral Energy Final Report for New Large Network Asset – Establishment of West Parramatta Zone Substation

Integral Energy has issued a Final Report for a “New Large Network Asset” in accordance with Clause 5.6.6 of the National Electricity Rules.

The Report contains a recommendation to establish a new zone substation in Macquarie St, Parramatta to alleviate existing load at risk and provide for the long term development of the Parramatta CBD and surrounding areas.

The total cost of the project recommended is $78.9m.

In accordance with Rules requirements, the Report will be placed on the NEMMCO and Integral Energy websites.  A copy of the document is available on the Integral Energy web site www.integral.com.au and can also be obtained from Integral Energy on telephone (02) 9853 6560.

Any enquiries in the first instance should be directed to:-

Ty Christopher
Manager, System Development
PO Box 6366
BLACKTOWN   NSW   2148

Email:              Ty.Christopher@integral.com.au
Phone:             (02) 9853 6560
Fax:                 (02) 9853 6099

 

pdf icon
587Kb

  Integral Energy Final Report for New Large Network Asset – Establishment of West Parramatta Zone Substation - 27 Oct 2008
  filename: 179-0651.pdf

 

Copyright © November, 2008 NEMMCO. All rights reserved. Access to and use of this site (including information or material contained in or accessed from this site) is subject to our Disclaimer and Reservation of Rights