Stakeholder Interaction > NSP Consultations >Powerlink & Transgrid : Potential Upgrade of Queensland / New South Wales Interconnector (QNI)

Powerlink & Transgrid : Potential Upgrade of Queensland / New South Wales Interconnector (QNI)

 
The Final Report has been prepared following consideration of submissions received in response to the Interim Report.

The Final Report concludes that it is premature to recommend a QNI augmentation option at this time. As a network augmentation is not being recommended at this time, TransGrid and Powerlink Queensland are publishing this Final Report for the information of Registered Participants and interested parties. This report is therefore not a Final Report required under the National Electricity Rules when recommending a network augmentation.

A summary of the Final Report will be placed on the NEMMCO website. A copy of the entire document can also be downloaded from TransGrid’s and Powerlink’s websites.

Any enquiries in the first instance should be directed to:

Enrico Garcia
Market Modelling Manager
TransGrid
PO Box A1000
Sydney South, NSW, 1235

Tel: (02) 9284 3017
enrico.garcia@transgrid.com.au

OR

Greg Hesse
Manager Regulation Strategies and Development
Powerlink Queensland
PO Box 1193
Virginia QLD 4014

Tel:  (07) 3860 2632
NetworkAssessments@powerlink.com.au

 
pdf icon
94Kb

  Powerlink & Transgrid Summary of Final Report : Potential Upgrade of Queensland / New South Wales Interconnector (QNI) – Assessment of Optimal Timing and Net Market Benefits - 13 Oct 2008
  filename: 179-0641.pdf

 

Copyright © November, 2008 NEMMCO. All rights reserved. Access to and use of this site (including information or material contained in or accessed from this site) is subject to our Disclaimer and Reservation of Rights