Power System Operations > Ancillary Services > Network Support & Control Services Review

Network Support & Control Services Review

NEMMCO is conducting a consultation to assist and inform NEMMCO in its review of Network Support and Control Services in the NEM (“the NSCS Review”).
This consultation is being conducted under clause 3.1.4(a1)(4) of the National Electricity Rules in accordance with the Rules consultation requirements detailed in clause 8.9 of the Rules.

NEMMCO released a "NSCS Review – Issues and Options Discussion Paper" (Discussion Paper) on Tuesday 29 July 2008 for First Stage of Rules consultation. 
Submissions closed on Tuesday 9 September 2008 and six submissions were received. There were no requests for meetings.

NEMMCO considered these submissions and released the “NSCS Review – Draft Determination Report” (Draft Determination) on Tuesday 25 November 2008.
NEMMCO is now conducting a Second Stage of Rules Consultation on this Draft Determination.

Submissions in response to the Notice of Second Stage of Rules Consultation should reach NEMMCO by 5:00pm on 16th February 2009, as notified in NEMMCO Communication 3187 on 24th December 2008. This date is a 2 week extension of the date originally notified on 25th November 2008.

NEMMCO will then consider submissions and release a Final Determination Report in March 2009.

Any enquiries regarding this NSCS review can be directed to Ross Gillett on (02) 9239 9114 or email ross_gillett@nemmco.com.au



81Kb
  Notice of Second Stage Consultation on NSCS Review - Updated - 29 Dec 2008
  filename: 168-0104.pdf


1550Kb
  Review of Network Support & Control Services - Draft Determination Report -25 Nov 2008
  filename: 168-0103.pdf
Background

Network Control Ancillary Services (NCAS) are transmission network services procured by NEMMCO that are critical to the maintenance of secure and reliable operation of the power system, by providing the capability to:

  • Maintain the transmission network within its current, voltage or stability limits following a credible contingency event; and
  • Enhance the net value of spot market trading by increasing transmission network power transfer capability within those limits.

NEMMCO is required under Clause 3.1.4(a1)(4) of the National Electricity Rules to conduct a review into the provision of NCAS, or NSCS in general (“the NSCS Review”), in consultation with Registered Participants, Intending Participants and interested parties and in accordance with Rules Consultation procedures.

Objectives of the Review

The objectives of the NSCS review are:

  1. To identify and address issues surrounding the current arrangements for the procurement and delivery of NSCS by TNSPs and NEMMCO; and
  2. To identify, evaluate and make recommendations on potential alternative arrangements for the more efficient procurement and delivery of NSCS, in accordance with the Rule obligation
Timeline for the Review Consultation Process

The following Table outlines key milestones in the NSCS Review consultation process.
Note that dates are indicative only, and may be subject to change by NEMMCO.

 

Process

Date

Release Draft Scoping Paper and invite submissions on scope of NSCS Review (4 weeks)

7 March 2008

Closing date for submissions on NSCS Review scope

4 April 2008

Release Final Scoping Paper and finalise NSCS Review scope

2 June 2008

First Stage Rules Consultation on Issues & Options

Release Issues & Options Discussion Paper
Invite submissions on NSCS issues and options



29 July 2008

Formal Commencement of NSCS Review – must complete within 12 months

Closing date for submissions on NSCS Issues & Options paper
(allow 6 weeks )

9 September 2008

Second Stage Rules Consultation on Draft Determination

Release Draft Determination Report
Invite submissions on Draft Determination Report



25 November 2008

Closing date for submissions on Draft Determination Report
(allow 8 weeks )

16 February 2009

Release Final Determination Report

20 March 2009

Submit proposed Rules to AEMC, to give effect to recommendations in the Final Determination Report

1 May 2009

 




79Kb
  Notice of First Stage Consultation on NSCS Review - 29 Jul 2008
  filename: 168-0098.pdf


972Kb
  Attachment A : NSCS Review - Issues and Options Discussion Paper -29 Jul 2008
  filename: 168-0099.pdf
 
Submissions to Issues & Options Discussion Paper:
  Energy Response   Grid Australia

  Hydro Tasmania

  NGF
  Transend   TRUenergy

 


 

223Kb
  Review of Network Support & Control Services : Final Scoping Paper - 03 Jun 2008
  filename: 168-0097.pdf
Submissions to Draft Scoping Paper:

  Energy Response   ESIPC

  Powerlink

  TRUenergy
Late Submission to Draft Scoping Paper
  Hydro Tasmania     

 


223Kb
  Review of Network Support & Control Services : Draft Scoping Paper - 07 Mar 2008
  filename: 168-0089.pdf

 

Copyright © November, 2008 NEMMCO. All rights reserved. Access to and use of this site (including information or material contained in or accessed from this site) is subject to our Disclaimer and Reservation of Rights