Operational Market Data > QLD Medium Term Outlook

QLD Medium Term Outlook

Download Graph Data

The MT PASA results do not provide complete modelling when some plant has long term energy restrictions typical of drought conditions. NEMMCO has undertaken additional modelling of energy restrictions due to the drought and the results in terms of likely capacity factors of NEM plant is contained in the attached report - Potential Drought Impact on Electricity Supplies in the NEM

 

Explanation of Graph Items

The following explains the source of the items on the above graph.  Note that all these items are forecast results from the MTPASA Reliability LRC run, and are relevant to the peak demand period of each day.

For further information on the MTPASA process: http://www.nemmco.com.au/powersystemops/432-0004.pdf

Generation:
Total generating capacity that is available within the selected region, based on the aggregate PASA Availability of all scheduled generation within that region (as advised by the relevant Generators), subjected to any network constraints and/or weekly energy limitations on that generation. This figure includes net export to other regions and excludes net import from other regions via interconnectors.

Demand:
Demand within the selected region forecast by NEMMCO with a 10% probability of exceedance, to be met by scheduled generation (either locally or via interconnector imports).

DSP (Demand Side Participation):
Total amount of committed demand reduction within the selected region in response to periods of high demand and high spot prices.  DSP is forecast by NEMMCO based on annual surveys of Network Service Providers, Retailers and other Customers.

Demand + Reserve:
Minimum generating capacity that is required to be available to the selected region locally and via interconnector imports to avoid a reserve shortfall in that region.

Net Import: (not shown on graph)
Net interconnector flow into the selected region from adjacent regions required to minimise the reserve shortfall in that region.

Reserve Shortfall:
Amount that (Generation + DSP + Net Import) available to the selected region falls below the (Demand + Reserve) requirement for that region.  Reserve shortfalls are represented by red vertical bars on the graph.

[Interconnector] Flow:
Flow on the relevant interconnector.


 Graph Item

 In terms of MMS Data Model…

Generation

 = MTPASA.REGIONSOLUTION.ConstrainedCapacity +
    MTPASA.REGIONSOLUTION.Unconstrained Capacity - DSP

 Constrained Capacity and Unconstrained Capacity are defined on pg 12 of the MTPASA Process   Description http://www.nemmco.com.au/powersystemops/432-0004.pdf

DSP
 Not Published (modelled in MTPASA as a dummy generating unit for each region)

Demand

 = MTPASA.REGIONSOLUTION.Demand10

Demand + Reserve

 = Demand + Minimum Reserve Level (MRL) requirement

 = MTPASA.REGIONSOLUTION.CapacityReq
 = MTPASA.REGIONSOLUTION.Demand10 +  MTPASA.REGIONSOLUTION.ReserveReq

 Further information on Minimum Reserve Levels can be found in the annual Statement of   Opportunities http://www.nemmco.com.au/about/040-0047.pdf

Net Import

 =  - MTPASA.REGIONSOLUTION.NetInterchangeUnderScarcity

Reserve Shortfall

 =  - Min { 0, Generation + DSP + Net Import – (Demand + Reserve) }
 =  - Min { 0, MTPASA.REGIONSOLUTION.SurplusReserve }

[Interconnector] Flow

  If Net Import > 0,
  then = MTPASA.INTERCONNECTORSOLUTION.CapacityMWFlow
  else = 0

 

 

Copyright © November, 2008 NEMMCO. All rights reserved. Access to and use of this site (including information or material contained in or accessed from this site) is subject to our Disclaimer and Reservation of Rights